What should a crane operator do prior to starting the crane?

  1. Analyze the daily weather report

  2. Conduct a pre-operational inspection

  3. Set the crane's maximum load limit

  4. Prepare the site for lifting

The correct answer is: Conduct a pre-operational inspection

Conducting a pre-operational inspection is a crucial step for any crane operator before starting the crane. This process involves checking various components of the crane to ensure that it is in safe working condition. The inspection typically includes examining the mechanical systems, checking the fluid levels, inspecting the rigging and safety equipment, and ensuring that all controls are functioning properly. This thorough review helps to identify any potential issues that could compromise safety during operations, thereby preventing accidents and equipment failures. While analyzing the daily weather report can help inform operational decisions, it does not directly relate to the crane's condition. Similarly, setting the crane's maximum load limit is an important task but generally follows the confirmation that the crane is operational. Preparing the site for lifting may also be necessary but should occur alongside or in conjunction with the pre-operational inspection. The primary focus before starting the crane should always be on ensuring the equipment itself is safe and reliable for use.