Why is it necessary to review site plans before crane operation?

  1. To understand site layout, obstacles, and lifting zones

  2. To estimate fuel costs for the crane

  3. To determine the crane's resale value

  4. To evaluate soil conditions for stability

The correct answer is: To understand site layout, obstacles, and lifting zones

Reviewing site plans before crane operation is crucial as it helps operators to gain a comprehensive understanding of the site layout, identify any potential obstacles, and determine designated lifting zones. Understanding the site layout allows the operator to visualize the work area, including surrounding buildings, power lines, and other infrastructure that may affect crane operation. Recognizing obstacles ensures that the operator can plan lifting paths, preventing accidents or mishaps during operations. Furthermore, identifying lifting zones is essential for safety and efficiency. Proper knowledge of these zones allows the operator to position the crane effectively and plan lifts that are safe and within the crane’s operational limits. This preparation minimizes risks, enhances safety, and improves the overall efficiency of lifting operations on the construction site. In contrast, estimating fuel costs for the crane, determining the crane's resale value, and evaluating soil conditions for stability, while they may play a role in overall project planning, do not directly address the immediate operational concerns that arise before starting to use the crane. Therefore, focusing on the site layout and obstacles is key to ensuring safe and effective crane operation.